Timeline

Following consultation with local residents and community groups, the Ironmonger Yard team will review the comments and then submit a final planning application to Medway Council for consideration in 2024.

What happens next?

It is hoped Medway Council will be able to make a decision this autumn, with the aim of getting construction under way by the end of 2024 or early in 2025.

01
10tH July 2024

Public exhibition

02
28tH July 2024

Public consultation closes

03
AUGUST 2024

Planning application submitted

04
End of 2024

Planning committee considers the application

05
Start of 2025

Work could get under way

06
Start of 2027

First homes ready for occupation